The topsides lifting campaign for the Liza Unity FPSO was recently completed and a major project milestone was achieved. Thanks to the efforts of the integrated team, over 26,000 tons of topsides were safely lifted in position at Keppel Shipyard in Singapore, since the vessel came out of dry-dock in October of last year.
All efforts are now focused on further progressing and completing the integration activities and gradually ramping-up the onboard commissioning activities.
The FPSO Liza Unity represents SBM Offshore’s first Fast4Ward® design, benefitting from standardization of the project`s execution plan and using a fully completed and commissioned MPF hull, which sets the benchmark for future FPSO projects. The project continues to target first oil in 2022 in line with client planning.